Water Mains
MDPE Communication and Supply Pipes
- Polyethylene Blue up to 63mm [BS 6572]
- Polyethylene – for underground cold water pipes
- PE Barrier Pipe (1 layer of metal + 2 layers of plastic) - supplies cald water to a 'brownfield site'
- Goose Neck – allows movement of a pipe
- Water Meter
- Supplier's External Stop Valve - located just before the boundary
Installation requirements
- Made of PVC-U [BS 3505]
- Pipes below ground SHOULD lay between 750-1350 mm or insulated
- Pipes entering buildings through walls below ground should be in duct and sealed at both ends
- For solid floors, if the pipe rises up inside the building less than 750mm from the outside wall, then vertical section must be insulated
- For suspended floor the pipe should be always insulated in the floor void
- A Main Stop Valve should be provided within 150mm of floor just insid the premises
- A Drain Valve should be fitted just above the Main Stop Valve
- 15mm – MIN size of a cold water service pipe to a dwelling